Repairs Set for South Bonneyview Bridge

Jul 8, 2013 5:12 PM

The City of Redding announced today it has formally signed a contract with Shasta Constructors Inc. to remove and reconstruct the approach slabs and bridge railing at both ends of eastbound South Bonnyview Bridge.

The city signed the contract for $286,000 to renovate the bridge which saddles the Sacramento River.

The project is set to begin on Friday, July 12 at 7 p.m. with the closure of the two eastbound lanes, which will last until Monday, July 15 at 5 a.m. During the closure, there will be one eastbound and one westbound lane available between Indianwood Drive and Bechelli Lane manned with traffic control and flaggers.

After the weekend closure, there will be two westbound lanes and one eastbound lane until the project’s expected completion date of August 30. The City of Redding advises all motorists to drive with caution when approaching these areas or avoiding them completely if possible.